Eathorpe Pumping Station
Scope of Work:
Severn Trent pumping station motor inverters were overheating, they required forced ventilation to remove heat from the inverters.
We designed and installed an extract canopy to remove heat from the inverters and installed supply fresh air into the room for additional ventilation.
The system was effective the inverters never failed after the installation.
Project date:
July 2023
Client:
Severn Trent Water
Location
Eathorpe Pumping Station